About the Project

JMT Civil were engaged to construct a 26-lot subdivision within the Shoalhaven Region of New South Wales. 

The scope of works involved 4,400cu.m earthworks, remediation, drainage installation, underground utilities, retaining walls, pavement construction and landscaping. 

Scope and Considerations

The team at JMT Civil were sought out due to their extensive experience in managing complex and competing challenges in this recently completed subdivision in such a environmentally significant region. 

Understanding that Civil works bring with them significant responsibility to protect and preserve the natural environment, allowed JMT Civil to complete the project whilst maintaining the pristine local surrounding environment.

 

Sustainable Considered Development

With sustainability principals in mind, the Team at JMT Civil undertook extensive planning in order to ensure the success of the project. Each aspect was carefully considered by our highly skilled team, from the initial clearing and earthworks through to the final landscaping.

  • Earthworks and Remediation: . In such a sensitive coastal area, these works were carefully managed to prevent soil erosion and sediment runoff, which can impact water quality and habitats. Any import or export of soil was carefully considered.

  • Tree Clearing: While clearing vegetation is often needed for new construction, both the client and JMT Civil sought to ensure that native trees are only cleared when absolutely necessary. Mitigation measures, such as the use of buffer zones, were utilised in order reduce the impact on surrounding vegetation and wildlife.

  • Drainage Installation: Through the construction of proper drainage systems, managing stormwater runoff and prevent flooding was on high importance. Through careful planning and consideration JMT provided drainage solutions in respect of local ecosystems, ensuring that runoff is managed without introducing pollutants or disrupting natural water.

Working closely with local stakeholder and suppliers, the subdivsion was deemed a huge success by the client and the local community. 

From road construction and drainage systems to site preparation and environmental management, JMT Civil has the technical expertise and local knowledge to handle any civil works challenge. 

Their dedication to safety, innovation, and sustainability makes them the partner of choice for both private and public sector developments in environmentally sensitive regions.